  "projectId": "microsoft-kirkkonummi",
  "reviewedAt": "2026-10-17T03:08:58.377713+00:00",
  "sources": [
    {
      "issuer": "Municipality of Kirkkonummi",
      "url": "https://kirkkonummi.fi/microsoftin-datakeskushankkeen-toisen-vaiheen-rakentamislupa-on-vireilla/",
      "publicationDate": "2025-03-14",
      "eventDate": "2025-03-14",
      "reviewed": "2026-10-16",
      "kind": "Original municipal permit notice",
      "text": "The municipality distinguishes permitted HEL04 from the then-pending HEL05–06 application LP-257-2024-02386, filed February 14, 2025.",
      "claimScope": "The municipality distinguishes permitted HEL04 from the then-pending HEL05–06 application LP-257-2024-02386, filed February 14, 2025.",
      "locator": "Paragraphs under the title; phase-one and phase-two scope",
      "accessible": true
    },
    {
      "issuer": "Microsoft",
      "url": "https://local.microsoft.com/blog/microsoft-aikoo-rakentaa-uuden-datakeskusalueen-etela-suomeen/",
      "publicationDate": null,
      "eventDate": null,
      "reviewed": "2026-10-16",
      "kind": "Original company construction update",
      "text": "The April 2026 update reports first-building facade/interior work and second-building foundations at Kirkkonummi; completion of Destia earthworks is not data-centre completion.",
      "claimScope": "The April 2026 update reports first-building facade/interior work and second-building foundations at Kirkkonummi; completion of Destia earthworks is not data-centre completion.",
      "locator": "Construction update April 2026; Sundsbergin yritystie 19 site-event address",
      "accessible": true
    },
    {
      "issuer": "Microsoft",
      "url": "https://news.microsoft.com/source/emea/2026/04/microsoft-kaynnistaa-paakaupunkiseudun-datakeskusalueen-toisen-vaiheen-rakentamisen/?lang=fi",
      "publicationDate": "2026-04-28",
      "eventDate": "2026-04-28",
      "reviewed": "2026-10-16",
      "kind": "Original company disclosure",
      "text": "Microsoft identifies three separate campuses and phased delivery; first-phase building work targets the turn of 2026–2027, followed by commissioning preparation. Second-phase permits are issuer-reported.",
      "claimScope": "Microsoft identifies three separate campuses and phased delivery; first-phase building work targets the turn of 2026–2027, followed by commissioning preparation. Second-phase permits are issuer-reported.",
      "locator": "Paragraphs 1–5; construction completion and commissioning are separate",
      "accessible": true
    },
    {
      "issuer": "DatacenterDynamics / Georgia Butler",
      "url": "https://www.datacenterdynamics.com/en/news/microsoft-acquires-470-acres-on-finlands-west-coast-for-data-center/",
      "publicationDate": "2026-06-09",
      "eventDate": "2026-06-09",
      "reviewed": "2026-10-16",
      "kind": "Independent specialist reporting; construction details attributed to Microsoft",
      "text": "DCD separately identifies Espoo, Kirkkonummi and Vihti as developments, while attributing site-progress details to Microsoft. Its Vaasa land acquisition is another project.",
      "claimScope": "DCD separately identifies Espoo, Kirkkonummi and Vihti as developments, while attributing site-progress details to Microsoft. Its Vaasa land acquisition is another project.",
      "locator": "Finland cloud-region background and links to all three local project updates",
      "accessible": true
    },
    {
      "issuer": "Fortum",
      "url": "https://www.fortum.com/services/heating-cooling/data-centres-helsinki-region",
      "publicationDate": null,
      "eventDate": null,
      "reviewed": "2026-10-16",
      "kind": "Original heat-offtake partner disclosure",
      "text": "Fortum identifies planned heat recovery from Espoo and Kirkkonummi. The roughly 40% district-heat contribution is a combined future network estimate, not IT capacity or present delivery.",
      "claimScope": "Fortum identifies planned heat recovery from Espoo and Kirkkonummi. The roughly 40% district-heat contribution is a combined future network estimate, not IT capacity or present delivery.",
      "locator": "Data centers provide electricity-based district heating; combined two-site scope",
      "accessible": true
    }
  ],
  "sourceIndependence": "Documents are counted as documents, not independent confirmations. Same-issuer releases and their rewrites share an underlying claim. Five documents; municipal notice establishes the historical application, not the present final legal disposition. Microsoft site/region updates share an issuer; DCD quotes those updates. Fortum corroborates the heat relationship, not compute commissioning.",
  "limitations": [
    "Five documents; municipal notice establishes the historical application, not the present final legal disposition. Microsoft site/region updates share an issuer; DCD quotes those updates. Fortum corroborates the heat relationship, not compute commissioning.",
    "No independently measured current operating IT load, utilisation, paid project expenditure or attributable site earnings established."
  ],
  "duplicateCheck": {
    "existingIdMatches": [],
    "aliasesChecked": [
      "Kolabacken",
      "HEL04",
      "HEL05",
      "HEL06",
      "Masala"
    ],
    "result": "No matching campus in serving 192-record inventory or queued new-project items; checked before integration",
    "scope": "Campus/location/legal aliases; Finnish three-site region is not separately counted as a parent project"
  },
  "wholeProjectRecertified": false,
  "aggregationEligible": false,
  "checkedRoleIds": [
    "checked-microsoft-kirkkonummi-MSFT"
  ],
  "checkedMeasurementIds": []
}