Expanded investment research / New Albany, Ohio — representative locality pin

Google New Albany: Central Ohio growth needs operator and campus separation

FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →

Project status: Existing operator-listed Ohio location; current campus acceptance and load undisclosed. Capacity scope: Campus IT MW and current utilization undisclosed. How we verify evidence.

← Back to project index

Compare this project → · Track its catalysts → · Evidence guide →

Research snapshot
Location
New Albany, Ohio — representative locality pin
Readiness
Existing facility / readiness unverified
Status
Existing operator-listed Ohio location; current campus acceptance and load undisclosed
Confirmed companies
Google / Alphabet
Next milestone
Campus-only capital allocation, useful load and resource-service readiness
Reviewed
October 6, 2026

Expanded analysis · Original disclosures linked below · CAD and USD preserved as labeled · Company statements attributed; interpretations labeled.

The one-minute investment takeaway

Our analysis: Central Ohio growth needs operator and campus separation. Google New Albany is a distinct project from the QTS location already covered. Its statewide scale should not be mistaken for site-level accepted computing or capital.

Readiness basis: Classification of evidence in the reviewed profile; strongest documented phase, not full-campus completion. Existing operator-listed Ohio location; current campus acceptance and load undisclosed Readiness source →

What the sources establish

Who receives the money?

Our analysis of disclosed roles. Revenue routes are business-model interpretations, not estimates of booked project revenue.

Company / exposureEconomic roleWhat investors need to establish
Google / AlphabetOwner or operator of the disclosed infrastructureAccepted useful capacity and net contribution after resource and renewal costs.
Named service and construction participantsContract-specific delivery and recurring service rolesActual contract, tariff or purchase terms; participation is not booked profit.
Equipment suppliers not established herePotential procurement and renewal spendingNamed awarded orders before attributing public-company project revenue.

How financially meaningful is it?

Our analysis: A regional cluster can share workforce and network capabilities while putting pressure on common electrical and construction resources. The investor model needs the actual campus’s delivered capital and accepted workloads, not a regional allocation chosen for convenience. Google’s Ohio footprint includes at least three identified locations; their investment and service milestones cannot be aggregated under New Albany. The nearby QTS site has a different owner and commercial model, even where representative map coordinates form a cluster. Google’s owner-user benefit arrives through cloud and product contribution rather than rent from itself. Underwrite equipment renewal, operating power and common infrastructure consistently across phases. An existing listing demonstrates the location’s role in the network, but current IT MW and campus-attributable financial results remain open diligence questions. Avoid treating regional cloud availability as a disclosure of a particular hall’s utilization.

How to test the economics

Computing contribution equals customer or product benefit minus power, network, facility operation, financing and equipment renewal. Model long-lived buildings separately from shorter-lived computing assets.

Hypothetical illustration: 10 MW steady IT load at 1.2 PUE uses 105,120 MWh annually. A USD 10/MWh tariff increase adds USD 1.0512 million annual cost. Neither load, PUE nor tariff is disclosed here; this is a sensitivity example, not a site forecast.

Milestones that would change the assessment

MilestoneEvidence to watch
Scope and capitalReconcile campus and portfolio figures, accepted versus potential capacity, and property versus equipment funding.
Electrical and cooling acceptanceCampus-specific expansion scope, operating load and renewal productivity. Equipment delivery, construction completion and commissioning are separate steps.
Commercial productivityUseful workloads or billable customer capacity, with operating costs and renewal obligations included.
Counterparty attributionNamed binding service and procurement terms before estimating participant earnings.

What could break the investment case?

Our analysis: Common utility bottlenecks, costly density upgrades and regional capital misallocation can weaken apparent returns. Shared geography does not establish shared ownership or tenants.

What would change our view?

Our analysis: Dated acceptance, improved useful output and competitive net resource costs would strengthen our assessment. Underutilized capacity, expensive upgrades without customer support, or rising renewal costs ahead of economic benefits would weaken it. We would update this profile using campus-specific operating and contractual evidence. A larger corporate investment headline, a grant program or a design capability alone would not establish a stronger return.

What remains unknown

Current accepted IT MW, facility load, billable occupancy or workload utilization, site-attributable earnings, tariff details, phase capital, supplier contract values and measured performance remain unestablished unless explicitly stated above. Operator specifications are not independently measured outcomes. The pin represents the locality rather than a verified server hall. Broad portfolio AI demand is not proof of a dedicated AI deployment here.

Project research for information, not a buy recommendation. Financial illustrations use assumptions, not disclosed site results or management guidance.

Company investor information & quarterly statements

Alphabet

Project participant recorded in reviewed project profile; consolidated corporate disclosure only

Official investor & shareholder information · Quarterly financial statements: 2026 Q2, quarter ended June 30, 2026

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →

Scoped FJI evidence check · October 16, 2026

Target: Ohio plans 2018; New Albany construction began 2019.

Dated evidence: Q2 2026 efficiency reporting identifies Central Ohio (New Albany); city describes active Google site.

Still open: Current site IT MW and capital deployment unavailable; $20B+ statewide investment spans multiple sites. Current phase occupancy, acceptance and legal parcel/permit reconciliation remain field-specific gaps; scoped review is not whole-project certification.

Sources: Google · Data Center Dynamics · Government agency · Google

Field-level review; original whole-profile dates and readiness classification retained. FJ Intelligence record →

Company research: documented roles

Follow the company profile for financial context. The evidence supports the specific role described here.

Role evidence does not establish project revenue, ownership economics, accepted capacity or a percentage of company sales.