Expanded investment research / Tukwila, Washington

DataBank SEA2: sell connectivity and usable density

FJI qualification held or pending: the full four-document gate, including project-specific government evidence, has not yet been accepted. Qualification evidence and decisions →

Project status: Existing marketed facility; historical expansion described separately. Capacity scope: 3 MW listed critical IT capacity; expansion snippet not added again. How we verify evidence.

← Back to project index

Compare this project → · Track milestones → · How to read the evidence labels

Research snapshot
Location
Tukwila, Washington
Readiness
Existing facility / readiness unverified
Status
Existing marketed facility; historical expansion described separately
Confirmed companies
DataBank
Next milestone
Current billable utilization and customer-specific liquid-cooling deployment
Reviewed
October 6, 2026

Expanded analysis · Original disclosures linked below · CAD and USD preserved as labeled · Company statements attributed; interpretations labeled.

The one-minute investment takeaway

Our analysis: SEA2 is a smaller colocation and connectivity asset with advertised density options. Its investment value should be tested through lease mix, cross-connect economics and the cost of supporting denser customers. Technical capability creates an opportunity; it does not prove AI equipment is installed or producing revenue.

Readiness basis: Classification of evidence in the reviewed profile; strongest documented phase, not full-campus completion. Existing marketed facility; historical expansion described separately Readiness source →

What the sources establish

Who receives the money?

Our analysis of disclosed roles. Revenue routes are business-model interpretations, not estimates of booked project revenue.

Company / exposureEconomic roleWhat investors need to establish
DataBankCabinet and cage rent, interconnection and service marginBillable power, connection volumes and customer-specific support costs.
Onsite carriersPotential network-service receiptsCustomer contracts and traffic; carrier count is not a revenue measure.
Cooling and electrical providersPotential density-upgrade procurementNamed awards and capital responsibility, rather than presumed AI purchases.

How financially meaningful is it? Analyst interpretation

Our analysis: a dense customer can increase rent per cabinet while consuming a disproportionate share of electrical and cooling capacity. Compare contribution per constrained kW rather than simply cabinet occupancy. Interconnection can support retention and service margin, but network presence must turn into paid connections. Expansion snippets and current specification tables need reconciliation before deriving any capacity growth rate.

How to test the economicsHypothetical model · not reported results

Contribution per constrained kW = net facility rent plus associated service margin minus customer-specific operating and capital burden, divided by allocated power capacity.

Hypothetical illustration: 20 cabinets using 25 kW each consume 500 kW. At USD 200 per kW-month, gross annual rent would be USD 1.2 million before costs. This illustrates capacity consumption and pricing assumptions, not SEA2 deployments or rates.

Milestones that would change the assessment

MilestoneEvidence to watch
Capacity reconciliationClarify how the historical addition relates to the current listed total.
Liquid-cooling acceptanceCustomer deployment, heat rejection, connection design and owner-versus-tenant costs.
Service monetizationPaid connections, retention and support margin rather than carrier count alone.

What could break the investment case?

Our analysis: Advertised density may depend on the specific room, equipment and cooling arrangement. A high-power tenant can exhaust available capacity while many cabinets remain empty. Undated expansion language can also create an inflated total if added to current specifications.

What would change our view?

Our analysis: Documented dense deployments with appropriate pricing and limited unrecovered capital would strengthen the case. Rising support costs, power exhaustion or expensive retrofits without compensated contracts would weaken it. An actual named AI workload would improve attribution beyond general HPC capability.

What remains unknown Not established in this review

Current billable capacity, workload mix, density approvals, liquid-cooling installation scope, expansion commissioning dates, price, maintenance capital, measured efficiency and tenant identities remain undisclosed in the listing.

Project research for information, not a buy recommendation. Financial illustrations use assumptions, not disclosed site results or management guidance.

Company investor information & quarterly statements

Corporate-disclosure certification held: Research packet retains a corporate disclosure hold.; Private participant disclosure/ownership exception remains unresolved.

DataBank: held-public-quarterly-disclosure-not-established

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →

Scoped FJI evidence check · October 16, 2026

Target: No current expansion service target established; SEA2 historical video Q4 2023 target kept separate.

Dated evidence: Existing marketed facility on retrieved operator page; commissioning date and measured utilization remain unverified.

Still open: Capital budget, dated commissioning, consumed/contracted MW and legal property entity unavailable. Historical 2MW expansion video may overlap current 3MW total and is excluded.

Sources: DataBank · DataCenterMap

Field-level review; original whole-profile dates and readiness classification retained. FJ Intelligence record →