Expanded investment research / Quincy, Washington — campus vicinity

Vantage Quincy / WA1: Completed construction leaves leasing and refresh economics to prove

FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →

Project status: Final-facility development completion announced in 2023; current billable load undisclosed. Capacity scope: 89 MW critical IT campus specification across three buildings. How we verify evidence.

Compare this project → · Track its catalysts → · Evidence guide →

← Back to project index
Research snapshot
Location
Quincy, Washington — campus vicinity
Readiness
Operating
Status
Final-facility development completion announced in 2023; current billable load undisclosed
Confirmed companies
Vantage Data Centers; Grant County Public Utility District
Next milestone
Current billable load, renewal terms and funded high-density upgrades
Reviewed
October 6, 2026

Expanded analysis · Original disclosures linked below · CAD and USD preserved as labeled · Company statements attributed; interpretations labeled.

The one-minute investment takeaway

Our analysis: Completed construction leaves leasing and refresh economics to prove. Quincy offers evidence beyond a land or power proposal: a developer-reported completed final building. That supports readiness of the property without disclosing every tenant’s installed compute or billable capacity. The hydro-rich region can reduce certain operating costs but does not eliminate tariff changes, demand charges or customer network requirements. Expansion and high-density retrofits should be evaluated on incremental returns rather than assumed attractive because historical facilities were built. Treat the 89 MW critical IT specification separately from power consumed and useful customer workload.

Readiness basis: Classification of evidence in the reviewed profile; strongest documented phase, not full-campus completion. Final-facility development completion announced in 2023; current billable load undisclosed Readiness source →

What the sources establish

Who receives the money?

Our analysis of disclosed roles. Revenue routes are business-model interpretations, not estimates of booked project revenue.

Company / exposureEconomic roleWhat investors need to establish
Vantage Data CentersRecurring property and retained service contributionAccepted and billable capacity, rents, retained service costs and maintenance
Named resource or service participantsUtility service, network provision or managed-fund ownership only where documentedContracts, billing scope and cost recovery; do not treat customer payments as automatic profit.
Other equipment and construction vendorsPotential capital-purchase receipts; no undisclosed vendor assignedActual orders and scope before attributing earnings or AI exposure.

How financially meaningful is it?

Our analysis: Quincy offers evidence beyond a land or power proposal: a developer-reported completed final building. That supports readiness of the property without disclosing every tenant’s installed compute or billable capacity. The hydro-rich region can reduce certain operating costs but does not eliminate tariff changes, demand charges or customer network requirements. Expansion and high-density retrofits should be evaluated on incremental returns rather than assumed attractive because historical facilities were built. Treat the 89 MW critical IT specification separately from power consumed and useful customer workload.

How to test the economics

Stabilized cash contribution = property and service receipts less retained operating expense, maintenance, allocated capital and finance costs.

Hypothetical illustration: A hypothetical 20 MW at USD 150/kW-month yields USD 36 million annual gross rent; a 10% billing reduction lowers it by USD 3.6 million. These are not Quincy leases or occupancy.

Milestones that would change the assessment

MilestoneEvidence to watch
Readiness and scopeCurrent billable load, renewal terms and funded high-density upgrades
Customer economicsNamed commitments and accepted equipment scope; reconcile recurring receipts, electricity recoveries, incentives and maintenance.
Capital and resourcesDocument the incremental power, cooling and network investment needed at the intended density; identify which party pays.
Evidence of useful outputFor owner-users, useful computing per dollar; for landlords, billable load and service margin; neither is inferred from a building count.

What could break the investment case?

Our analysis: Customer concentration, retrofit costs and lease renewal economics remain after development completion. Low-power-price marketing is not a current customer tariff quote and does not establish total delivered compute cost.

What would change our view?

Our analysis: Phase-specific customer acceptance, sustained useful workloads and cash generation after recurring costs would strengthen our assessment. Missed acceptance, deteriorating margins or additional capital required without equivalent contract protection would weaken it. A larger design envelope alone would not change the operating assessment.

What remains unknown

Current phase utilization, site-specific cash flow, customer acceptance detail, actual tariff, measured PUE, maintenance obligations and incremental capital returns are not fully disclosed in the reviewed sources. Coordinates represent the named locality or campus vicinity, not a surveyed building. A target date is not a verified completion. Building area is not IT MW, and utility or generation capacity is not automatically campus computing capacity.

Project research for information, not a buy recommendation. Financial illustrations use assumptions, not disclosed site results or management guidance.

Company investor information & quarterly statements

Corporate-disclosure certification held: Research packet retains a corporate disclosure hold.; Private participant disclosure/ownership exception remains unresolved.

Vantage: held-public-quarterly-disclosure-not-established

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →

Scoped FJI evidence check · October 16, 2026

Target: 2011 initial campus development; WA13 construction started late 2022.

Dated evidence: Vantage October 18, 2023 announces third/final WA13 delivery, corroborated by DCD October 19.

Still open: Actual tenant-accepted or billable MW and metered load undisclosed; 89MW campus and 64MW WA13 overlap and cannot be summed. Current phase occupancy, acceptance and legal parcel/permit reconciliation remain field-specific gaps; scoped review is not whole-project certification.

Sources: Vantage Data Centers · Data Center Dynamics

Field-level review; original whole-profile dates and readiness classification retained. FJ Intelligence record →