AVAIO Digital Taurus, Brandon, Mississippi
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
Project status: Company-reported sitework; September 24, 2026 local visit found clearing but no structures; August 2027 occupancy target. Capacity scope: 116 MW Phase 1 planned power; 1,036 MW marketing envelope unverified as committed or energized. How we verify evidence.
Compare this project → · Track its catalysts →
← Back to project index- Location
- Brandon, Mississippi
- Readiness
- Under construction — documented phase
- Capacity & scope
- 116 MW Phase 1 planned power; 1,036 MW marketing envelope unverified as committed or energized
- Named companies
- AVAIO Digital; Entergy Mississippi; Yates Construction
- Next milestone
- Dated structural progress, phase-specific utility delivery and customer acceptance; August 2027 issuer occupancy target
- Reviewed
- October 7, 2026
Approximate locality marker. Construction-stage classification does not mean every planned phase is permitted, energized or serving customers.
Investment takeaway
Taurus has moved beyond announcement through an executed electric-service agreement and company-reported sitework with a named contractor. Its changing occupancy target and enlarged capacity marketing warrant phase-specific treatment rather than treating the entire campus as ready.
Delivery commitments and dated checkpoints
Scoped source review · October 16, 2026. Earlier full-profile dates remain recorded; business events retain their actual dates.
Dated physical checkpoint
The Clarion Ledger’s October 11, 2026 report, reviewed through its accessible AOL syndication, describes a September 24 site visit at Taurus in Brandon. The reporter observed clearing and machinery but no structures. This is a dated, attributed physical observation—not a finding that underground work was absent, construction had stopped, the project was cancelled or the site remains unchanged today. The article reported no company response to its requests at publication. (Mississippi Clarion Ledger / Bea Anhuci, accessible AOL syndication)
Plan versus actual
AVAIO’s September 10, 2025 release announced sitework, Yates Construction and an August electric-service agreement. It forecast first-half 2027 occupancy and Phase 1 completion/energization. The undated live project page now presents August 2027 first occupancy. Preserve both dated targets and their different wording; no exact delay in days is established. Neither source proves accepted service or current delivered capacity. (AVAIO Digital; AVAIO Digital)
Investor read-through and next checkpoint
Our analysis: the useful next checkpoint is visible structural progress accompanied by phase-specific utility delivery and customer acceptance, not another groundbreaking label. Incentive support in the governor’s announcement does not certify all campus permits. Rankin First’s service-agreement approval statement remains attributed because the MPSC order was not retrieved. Keep planned power separate from operating IT load, and announced investment separate from paid construction costs. (Office of Governor Tate Reeves; Rankin First)
Site and scope
AVAIO identifies a 329-acre site at East Metropolitan Center in Brandon, Rankin County. The initial announcement described 175 acres; DCD explicitly identified the discrepancy and sought clarification. The current 329-acre figure remains attributed to AVAIO.
Power basis
AVAIO says an Entergy Mississippi ESA was executed in August 2025. Its construction release specified 116 MW of Phase 1 power capacity, not independently verified IT capacity. The current page advertises a 1,036 MW long-term baseload envelope including 536 MW grid and 500 MW behind-the-meter supply; this is not verified energized or fully committed capacity.
Capital and financing
Promoters describe an initial $6 billion investment. No project-level financing close, lender terms, customer lease value or earnings contribution was established. The announced amount should remain an investment plan rather than money proven spent.
Demand and economic roles
AVAIO is the private developer, owner and operator; Yates Construction is the named general contractor; Entergy Mississippi is the utility. MDA provides incentive support and Rankin First supports the industrial site. Named customers, GPU vendors and contracted customer MW were not established.
Construction milestones
Strongest documented phase only; no whole-campus completion inferred. Company-reported sitework; September 24, 2026 local visit found clearing but no structures; August 2027 occupancy target
Government and utility record limits
The governor’s announcement records MDA tax-exemption approval. Rankin First’s detailed FAQ says the Entergy agreement was approved by MPSC and assigns interconnection costs to the customer. The MPSC order, docket identifier, approval date and full conditions were not retrieved; attribute that claim to Rankin First.
Water and community considerations
AVAIO describes water infrastructure, sewer extension work and recycled-water options. Rankin First distinguishes non-evaporative Phase 1 cooling from possible graywater use in future phases. WLBT’s original document-based reporting records Brandon residents’ clearing, grading and drainage concerns; those concerns do not establish a permit violation.
Risks and unknowns
Customer demand, financing, electric delivery, later behind-the-meter generation approvals and drainage conditions remain material uncertainties. Campus building and air permit identifiers were not established. Company-reported sitework supports construction-stage coverage, not a finding that every phase is fully permitted.
What would change the assessment
Retrieved permits and the MPSC order, measurable building progress, disclosed signed customer commitments and actual energization would strengthen the assessment. Further timetable changes, financing gaps or unresolved generation and water conditions would weaken it.
Coverage and scope
Adds distinct private Taurus development and utility-service execution in Mississippi. One Taurus campus at East Metropolitan Center; Phase 1 sitework does not establish approval of later generation.
Financial significance and assumptions
Promoters describe an initial $6 billion investment. No project-level financing close, lender terms, customer lease value or earnings contribution was established. The announced amount should remain an investment plan rather than money proven spent.
Our analysis: construction can precede customer billing and cash returns. No utilization, pricing, margin or project earnings model is assumed. Investment plans, financing facilities and money spent are different quantities.
Listed company connections
- ETR: Utility parent; executed service agreement reported by AVAIO, delivered capacity and earnings unverified.
Government record audit
Mississippi Public Service Commission · Record / evidence ↗. Reviewed October 7, 2026.
- Identifier
- not established
- Record type
- Utility service agreement approval claimed by Rankin First
- Applicant / entity
- not established
- Filed
- not established
- Decision
- not established
- Status
- Company-reported sitework; September 24, 2026 local visit found clearing but no structures; August 2027 occupancy target
- Phase scope
- Entergy Phase 1 service agreement, not whole-campus generation approval
- Conditions / limits
- Order, legal applicant and conditions not verified.
Source basis and claim audit
7 distinct reviewed documents. Primary evidence and independent reporting are identified below; syndicated releases count once. Sources establish only the stated claim, not whole-campus completion.
AVAIO Digital ↗ · Primary evidence. Published 2025-09-10; event not separately established; reviewed October 7, 2026.
Sitework underway, Entergy ESA executed August2025, Yates Construction GC; 329 acres, Phase1 >600k sqft/116MW power; historical H1 2027 delivery target.
AVAIO Digital ↗ · Primary evidence. Published undated live page; event not separately established; reviewed October 7, 2026.
First occupancy now August2027,329acres; executed ESA for 2027; company says zoned; sewer extension underway and recycled water option; enlarged long-term power figures. No proof later generation/BTM permits/financing. Don't retain obsolete H1 target as current.
Office of Governor Tate Reeves ↗ · Government record. Published 2025-08-19; event not separately established; reviewed October 7, 2026.
MDA Data Center Enterprises tax exemption approval/site grants and Entergy participation. Incentive is not construction completion. Confirm exact date header if displaying (search reports Aug19; initial OPEN excerpt omitted header).
City of Brandon ↗ · Government record. Published 2025-08-22; event not separately established; reviewed October 7, 2026.
City confirms operator/site/AI-ready plan but historical175acres; promotions/quotes overlap initial release, don't count same shared statements as independent corroboration.
DatacenterDynamics ↗ · Independent reporting. Published 2025-09-13; event not separately established; reviewed October 7, 2026.
Specialist reporting of sitework/Yates and independent editorial identification of175vs329-acre discrepancy; sought clarification. Underlying sitework claim company-reported, not reporter onsite.
Rankin First ↗ · Primary evidence. Published undated live FAQ; event not separately established; reviewed October 7, 2026.
Distinct substantive local project disclosure: Phase1 draws116MW; says Entergy agreement MPSC approved/customer pays interconnection; building-permit process still applies; power, cooling and fiscal terms described. MPSC docket/date/order NOT independently retrieved. Attribute claimed approval to Rankin First; no docket invented. Closed-loop Phase1 and graywater future phases; marketing household comparisons/savings not independently established.
WLBT ↗ · Independent reporting. Published 2026-07-29; event not separately established; reviewed October 7, 2026.
Obtained consultant documents via records request; Brandon residents raised clearing/grading/drainage concerns. Does not imply Jackson moratorium applies Brandon. Distinct original local scrutiny; only Brandon-specific facts useful here.
October 16 source-check scope
- Dated physical observation. In its October 11, 2026 report, the Clarion Ledger describes a September 24 visit that found clearing and machinery but no structures. This is the reporter’s dated observation, not an FJ site visit or proof of a halt, absent underground work or the site’s current condition. Mississippi Clarion Ledger / Bea Anhuci, accessible AOL syndication · 2026-10-11
- Earlier delivery target. AVAIO’s September 10, 2025 release forecast first-half 2027 occupancy and Phase 1 completion/energization, naming Yates Construction and reporting an August electric-service agreement. These were issuer forecasts, not actual acceptance. AVAIO Digital · 2025-09-10
- Current published target. AVAIO’s undated project page, checked October 16, 2026, forecasts first occupancy in August 2027. The page revision date is unknown. This target differs from the earlier wording; no precise delay or missed delivery date is established. AVAIO Digital · publication date unavailable
- Official scope. The August 19, 2025 governor’s announcement establishes project-specific MDA incentive support, not all construction/environmental permits or power acceptance. Office of Governor Tate Reeves · 2025-08-19
- Power-record limit. Rankin First says MPSC approved the Entergy service agreement. This remains attributed to the development body: the controlling order, approval date and conditions were not retrieved. Rankin First · publication date unavailable
Related Spotlight · what the dated site record establishes before 2027 →
Company investor information & quarterly statements
Corporate-disclosure certification held: Research packet retains a corporate disclosure hold.; Private participant disclosure/ownership exception remains unresolved.
Entergy
Electric utility / power relationship; not campus ownership
Official investor & shareholder information · Quarterly financial statements: Q2 2026 ended June30 2026
AVAIO: held-public-quarterly-disclosure-not-established
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →