Expanded investment research / Tsukuba, Ibaraki, Japan

Goodman TYO05 Tsukuba

FJI qualification held or pending: the full four-document gate, including project-specific government evidence, has not yet been accepted. Qualification evidence and decisions →

Project status: First 50 MW phase under construction and leased; full 1 GW envelope is not delivered capacity. Capacity scope: 50 MW leased first phase; 1,000 MW power-secured campus envelope reported by developer. How we verify evidence.

Project and ownership

Goodman Group; hyperscale tenant undisclosed. One named campus or explicitly bounded multi-campus development; reported envelopes are not operating IT load.

Power, permits and delivery

First 50 MW phase under construction and leased; full 1 GW envelope is not delivered capacity

Financing and economics

A 20-year 50 MW lease is reported; tenant identity and campus-level returns are undisclosed.

Investor implications · Our analysis

Public-record evidence narrows development uncertainty but does not establish utilized compute, billable capacity, attributable earnings or a stock recommendation.

What to watch next

First-phase completion, grid energization and tenant acceptance

Risks and unknowns

Tenant identity, delivered IT load, construction acceptance, later-phase commitments and full-campus funding remain unverified.

Sources and verification

Four project-specific sources reviewed, including at least one public-agency record.

  1. Developer capacity disclosureGoodman Group

    Goodman’s pipeline identifies TYO05 with 50 MW leased and a 1,000 MW full-campus power envelope.

  2. Local government development recordTsukuba City

    Tsukuba records a decision to construct the first data-centre building and associated infrastructure.

  3. Independent specialist reportingDatacenterDynamics

    DCD reports a 20-year lease for the 50 MW first phase and distinguishes it from the 1 GW plan.

  4. Independent reportingReuters

    Reuters reports construction of the first 50 MW phase and community opposition.

Reviewed October 7, 2026 · Source audit

Company investor information & quarterly statements

Corporate-disclosure certification held: GMG: Actual official half-year statements read, PDF83pages, but quarterly financial statements not established. Do not relabel half-year financials as quarterly.; Research packet retains a corporate disclosure hold.

Goodman Group

Named developer; hyperscale tenant undisclosed, do not infer Microsoft/Google.

Disclosure verification held: Actual official half-year statements read, PDF83pages, but quarterly financial statements not established. Do not relabel half-year financials as quarterly.

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →

Scoped FJI evidence check · October 16, 2026

Target: First phase early 2028 per August 2026 reporting. Old city approximately-three-year early-facility target is mixed-use scope, not all DC completion.

Dated evidence: City progress disclosure and signed lease reported; no operational load established.

Still open: Current Goodman pipeline extraction omitted project details; search index shows TYO05 50 MW leased/1,000 MW secured. TKO05 vs TYO05 spelling needs reconciliation. Land sale JPY11.029bn is mixed-use land, excluded from DC capex. Latest Reuters October 7 access failed; indexed report flags opposition, not cancellation.

Sources: Tsukuba City · DatacenterDynamics · Goodman

Field-level review; original whole-profile dates and readiness classification retained. FJ Intelligence record →

Company research: documented roles

Follow the company profile for financial context. The evidence supports the specific role described here.

Role evidence does not establish project revenue, ownership economics, accepted capacity or a percentage of company sales.