Google Skien / Gromstul campus
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
Published and scoped evidence reviewed October 16, 2026. Historical source events retain their own dates.
Google / Alphabet research · FJI evidence · Compare · Milestones · European coverage
Project at a glance
- Location
- Gromstul area, Skien, Norway
- Status
- Construction and fit-out awards documented; Google’s current inventory still labels Skien in development
- Capacity scope
- 240 MW first-phase allocation, not metered operating IT load.
- Business model
- Phased hyperscale cloud and AI-supporting infrastructure
- Next milestone
- Find a dated Google opening/commissioning record and phase-specific accepted electrical capacity.
Representative locality-area pin, not a surveyed campus boundary or entrance.
Construction evidence
The municipality describes activity at Gromstul after the February 2024 start announcement. The contractor subsequently disclosed a fit-out award.
Power and budget
Google’s EUR600 million announcement covers the data centre and related infrastructure. Its 240 MW allocation is not proof of installed or utilised IT load; broader area-wide power figures must remain separate.
Investor read-through
Our analysis: allocated power and a fit-out contract are useful progress checkpoints. A 2026 operating target still needs a dated commissioning or service-start actual.
Delivery commitments and dated checkpoints
Target: 2026 opening was the issuer’s original target; no verified operating actual found in this source set.
- Undated current source: Skien identifies Google’s Gromstul land purchase and first-stage construction announcement in February 2024, with subsequent site activity. Project-specific municipal project account
- 2024-02-07: Google announces EUR600 million for the Skien data centre and related infrastructure, a 240 MW first-phase allocation, and a 2026 operating target. Allocation is not metered IT load. Original issuer release; NTB is distributor
- 2024-12-18: ZAUNERGROUP reports a specialist fit-out award for Google’s VLB campus in Skien, retaining a 2026 target. Contract value and accepted capacity are not disclosed. Original contractor award disclosure
- 2024-02-08: DCD reports Skien groundbreaking and distinguishes the 240 MW allocation from the much larger long-term area-wide power figure. Independent specialist reporting
- Undated current source: Google continues to list Skien as in development in its European location inventory. Original current company location listing
Unavailable: no matched, comparable accepted operating-IT target and actual.
Company connections
Google sponsors the Gromstul campus. ZAUNERGROUP reports a fit-out award; no contract value or site supplier revenue is established.
Google / Alphabet research · FJI evidence · Compare · Milestones · European coverage
What remains unverified
Energization, commissioning, accepted customer capacity, current operating IT MW, utilisation, project spending and campus earnings remain unverified. Exact allocation boundary, phased energization and final operating date remain open.
Next observable evidence
Find a dated Google opening/commissioning record and phase-specific accepted electrical capacity.
Sources and claim boundaries
Documents are counted as documents, not independent confirmations. Same-issuer releases and their rewrites share an underlying claim. Five documents across municipality, Google, contractor and DCD. NTB distributes Google’s release and is not an independent corroborator. The current Google location listing remains in development; no inference from another tracker’s operating label is accepted.
- Municipality of Skien · Document date not displayed; dated subsection retained
Skien identifies Google’s Gromstul land purchase and first-stage construction announcement in February 2024, with subsequent site activity.
Project-specific municipal project account · Google etablering i Skien kommune; introductory paragraph · Checked 2026-10-16
- Google Norge via NTB press-release service · 2024-02-07
Google announces EUR600 million for the Skien data centre and related infrastructure, a 240 MW first-phase allocation, and a 2026 operating target. Allocation is not metered IT load.
Original issuer release; NTB is distributor · Opening construction announcement; infrastructure bullet on first-phase allocation; investment paragraph · Checked 2026-10-16
- ZAUNERGROUP · 2024-12-18
ZAUNERGROUP reports a specialist fit-out award for Google’s VLB campus in Skien, retaining a 2026 target. Contract value and accepted capacity are not disclosed.
Original contractor award disclosure · ZAUNERGROUP expands Google’s data center; opening paragraph · Checked 2026-10-16
- DatacenterDynamics / Dan Swinhoe · 2024-02-08
DCD reports Skien groundbreaking and distinguishes the 240 MW allocation from the much larger long-term area-wide power figure.
Independent specialist reporting · Groundbreaking account and power-scope clarification · Checked 2026-10-16
- Google · Document date not displayed; dated subsection retained
Google continues to list Skien as in development in its European location inventory.
Original current company location listing · Our locations → Europe → Skien, Norway (in development) · Checked 2026-10-16
AI-assisted public-source research by Fjord Journal. No original interviews, site visits, independent metering or whole-project certification. Planned investment and capacity are excluded from delivered-IT and paid-spending aggregates. Unknown values remain unavailable.
Company investor information & quarterly statements
Alphabet
Google sponsors the Gromstul campus. ZAUNERGROUP reports a fit-out award; no contract value or site supplier revenue is established.
Official investor & shareholder information · Quarterly financial statements: 2026 Q2, quarter ended June 30, 2026
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →