Flagship research / Texas / Abilene

Stargate Abilene

FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →

Latest evidence check · October 16, 2026

Company-reported delivery: On its September 10, 2026 earnings call, Oracle management said six of the campus’s eight buildings, representing 618 MW and 75% of its stated capacity, had been delivered to the customer. This is an attributed delivery statement. It does not independently establish energized IT load, utilization or full-campus completion. Published earnings-call transcript →

A separate expansion: Reuters reported on March 6, citing Bloomberg and people familiar with the matter, that Oracle and OpenAI were no longer pursuing a proposed additional 600 MW near Abilene after negotiations over financing and changing capacity needs. Reuters also reported that this capacity would be fulfilled at other campuses. This is separate from the existing 1.2 GW planned campus envelope and the adjacent Microsoft development; it does not establish cancellation of the existing campus or financing as the sole cause. Reuters scope and attribution →

Still open: Independent capacity measurement and its power basis, commissioning of the remaining buildings, utilization, site pricing and project-level economics. Do not multiply the 75% statement by the 1.2 GW planned envelope to invent operating IT capacity. The end-2026 second-phase date below remains a historical developer target.

Targeted evidence update, not whole-project recertification. Original profile review: October 6, 2026. FJ Intelligence evidence register →

Project status: Oracle management reported six of eight buildings, representing 618 MW (75% of stated campus capacity), delivered to its customer on Sept. 10, 2026; this is customer-reported delivery, not independently measured IT load. Capacity scope: 1.2 GW planned campus envelope; adjacent 900 MW Microsoft project separate. How we verify evidence.

← Back to project index

Compare this project → · Track milestones → · How to read the evidence labels

Research snapshot
Location
Texas / Abilene
Readiness
Operating
Status
Oracle management reported six of eight buildings, representing 618 MW (75% of stated campus capacity), delivered to its customer on Sept. 10, 2026; this is customer-reported delivery, not independently measured IT load.
Company
Crusoe, Oracle, OpenAI, NVIDIA and Lancium
Next milestone
Commissioning of the remaining Oracle/OpenAI buildings; delivered and utilized compute.
Scoped check
October 16, 2026

Expanded analysis · Original disclosures linked below · Amounts in USD · Company claims attributed; analyst interpretations labeled.

The one-minute investment takeaway

Abilene is a documented AI workload story, not simply a land or construction announcement. Oracle provides the compute service used by OpenAI; Crusoe delivers the physical infrastructure. The investor test is whether additional capacity becomes billable compute quickly enough to justify its financing and equipment costs.

Readiness basis: Classification of evidence in the reviewed profile; strongest documented phase, not full-campus completion. Oracle reports 75% of capacity delivered as of September 2026; remaining delivery pending Readiness source →

What the sources establish

Who receives the money?

Our analysis of the disclosed company roles. Revenue routes below are business-model interpretations, not estimates of booked project revenue.

Company / exposureEconomic roleWhat investors need to establish
Oracle / ORCLCloud infrastructure services to the compute customer.Recurring service revenue is the route to monetization; site billing, pricing and margins are not public.
Crusoe / privateDevelopment and physical infrastructure delivery.Infrastructure arrangements are distinct from Oracle’s compute revenue; lease and financing terms need separate evidence.
NVIDIA / NVDAConfirmed GB200 hardware connection.Equipment deliveries support a supplier opportunity; replacement orders and campus-specific revenue remain undisclosed.
OpenAI / privateUses the compute capacity for AI workloads.Model usage and customer demand underpin the economic case; campus spending is a cost to the user, not its revenue.

How financially meaningful is it? Analyst interpretation

Oracle reported FY2026 cloud infrastructure revenue of USD 18.1 billion and negative USD 23.7 billion free cash flow. These are company-wide results, not Abilene results. Our analysis: the relevant tension is rapid infrastructure revenue growth alongside upfront funding needs. Backlog is valuable only as delivery converts it into recognized revenue and cash; the campus’s share of either measure is unknown. Financial disclosure ↗

How to test the economicsHypothetical model · not reported results

Delivered accelerator-hours × billable utilization × net realized price = modeled compute revenue. Subtract power, operating expenses, hardware depreciation and financing or infrastructure costs to assess returns.

Illustration, not a site forecast: moving utilization from 50% to 70% increases billable hours by 40% at unchanged available capacity and pricing. A 20% price decline would reduce that revenue improvement to 12%. More hardware alone does not guarantee proportionally higher profit.

Milestones that would change the assessment

Milestone / disclosed targetEvidence to watch
By end-2026: operator targetDated completion and commissioning evidence for the six additional buildings; do not infer success from the target date.
After equipment deploymentEvidence that installed racks are delivering customer workloads; energized buildings and utilized hardware are different milestones.
At subsequent Oracle resultsRevenue conversion, capital spending and financing disclosures. Portfolio metrics provide context rather than campus attribution.

What could break the investment case?

Our analysis: The delivery target has already shifted. Slower power or equipment commissioning would defer billing while some costs continue. Concentrated compute demand, financing expense and faster hardware obsolescence could compress returns even if the campus is completed.

What would change our view?

Our analysis: We would weaken the economic thesis if commissioning slips without matching customer protections, if available compute grows faster than paid usage, or if realized pricing falls faster than unit costs. We would strengthen it with verified utilization, stable contracts and improving cash conversion.

What remains unknown Not established in this review

No verified current full-campus IT load, campus utilization, realized compute prices, specific lease rates or project-level profit. The full site’s planned power capacity, Stargate-wide spending commitments and Oracle’s company backlog are three different quantities.

This is project research, not a valuation model or a buy recommendation. Financial illustrations are assumptions, not management guidance. Review current company filings and valuation before making an investment decision.

Further reporting

Independent coverage to read alongside the primary evidence. Subscription may be required. Links reviewed October 6, 2026; historical reports do not establish current project readiness.

Our reading focus: distinguish the existing campus from expansion plans, assess the reliability of its power strategy, and separate temporary construction activity from permanent employment. Bloomberg’s full report was not accessible during this review; it is included as further reading, not as the basis for a new factual claim.

Company investor information & quarterly statements

Corporate-disclosure certification held: Research packet retains a corporate disclosure hold.; Private participant disclosure/ownership exception remains unresolved.; Private participant disclosure/ownership exception remains unresolved.; Private participant disclosure/ownership exception remains unresolved.

Oracle

Project participant recorded in reviewed project profile; consolidated corporate disclosure only

Official investor & shareholder information · Quarterly financial statements: Q1 FY2027 ended2026-08-31

NVIDIA

Project participant recorded in reviewed project profile; consolidated corporate disclosure only

Official investor & shareholder information · Quarterly financial statements: Q2 FY2027 ended2026-07-26

Crusoe: held-public-quarterly-disclosure-not-established

OpenAI: held-public-quarterly-disclosure-not-established

Lancium: held-public-quarterly-disclosure-not-established

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →

Company research: documented roles

Follow the company profile for financial context. The evidence supports the specific role described here.

Role evidence does not establish project revenue, ownership economics, accepted capacity or a percentage of company sales.