- Source document · published date not established · reviewed Not established
Issuer identifies 44 MW powered capacity, 13,800 GB300 GPUs and European 200 MW ambition; none is proof of installed utilization.
- Source document · published date not established · reviewed Not established
Two funding tranches of approximately USD 720m and EUR 94m; identifies the seven-bank syndicate and GPU procurement purpose.
- Source document · published date not established · reviewed Not established
Independent reporting of USD 830m debt and the original Q2 2026 operating target; not current commissioning confirmation.
- Source document · published date not established · reviewed Not established
Reports construction launched and planned service in Q2 2026. Supports a dated construction classification, not October operation.
- Source document · published date not established · reviewed Not established
Reports SIN01’s first full operating-year performance; annual renewable matching and measured water figures distinguish operations from targets.
- Source document · published date not established · reviewed Not established
Announces Microsoft agreement, 66,000+ Rubin GPUs starting late 2027, EUR 230m shared infrastructure and EUR 465m second building.
- Source document · published date not established · reviewed Not established
Independent reporting of 26 MW SIN01, expanded compute agreement, second-building investment and future deployment schedule.
- Source document · published date not established · reviewed Not established
Identifies Microsoft agreement and 30,000+ Rubin GPUs in 2027 at the 230 MW campus.
- Source document · published date not established · reviewed Not established
Identifies USD 790m committed financing and separate USD 790m uncommitted accordion for another 115 MW.
- Source document · published date not established · reviewed Not established
Reports three North Campus buildings totaling 100 MW, works underway and 2027 completion expectation.
- Source document · published date not established · reviewed Not established
Independent reporting of financing and Microsoft capacity relationship replacing the earlier OpenAI plan.
- Source document · published date not established · reviewed Not established
Establishes Aker partnership, hydropower rationale and historical Stargate/OpenAI plan; does not verify the current customer contract.
- Florida Senate · published 2025-03-06 · reviewed 2026-10-08
LFIR 3066 requests $24 million for University of Florida AI Leadership Technology Renewal / HiPerGator Updates, through the Board of Governors, including NVIDIA networking. This project-specific state record is a funding request, not an enacted appropriation, cash receipt or final contract.
- University of Florida · published 2025-10-15 · reviewed 2026-10-08
Public university disclosure records the East Campus launch and reports a $33 million purchase, 63 NVIDIA DGX B200 nodes and 504 GPUs replacing the earlier A100 SuperPOD. Performance comparisons are issuer claims and not comparable campus MW. The purchase figure differs in scope/date from the earlier $24 million budget/request.
- The Independent Florida Alligator / Madeline Herring · published 2025-10-15 · reviewed 2026-10-08
Original on-site journalism documents the October 14 ribbon cutting and media tour, the East Campus location and the December 2024 $24 million trustee allocation. Energy-efficiency assertions are attributed to directors; it does not establish a power tariff or measured IT load.
- Mainstreet Daily News / Nick Anschultz · published 2025-10-14 · reviewed 2026-10-08
Original reporting and photographs document the launch and guided data-center tour. It distinguishes the earlier $24 million trustee investment from the computing generations and attributes NVIDIA installation involvement to UF. Research-budget figures discussed at the event are not project revenue.
- Israel Innovation Authority · published 2026-01-18 · reviewed 2026-10-08
Project-specific government authority confirms Nebius national-supercomputer infrastructure is live and operational, opening subsidized-access allocation. Describes 1,000 B200 accelerators and 70% industry / 30% research allocation. This confirms computing service, not a comprehensive site permit or measured utilization.
- Israel Innovation Authority · published 2025-05-14 · reviewed 2026-10-08
Government tender-award disclosure selects Nebius for national computing infrastructure, with projected investment exceeding NIS500 million including NIS160 million government support. Award and support amounts are not proof of cash disbursement or incurred expenditure. English/Hebrew versions are one underlying document.
- Israel Innovation Authority · published date not established · reviewed 2026-10-08
Current official voucher call identifies Nebius as operator and a 1,000-B200 monthly allocation framework; 30% industry and 80% academic price discounts subject to eligibility and committee approval. Open date January 1 is not publication date. Detailed future application windows are not actual utilization or recipient awards.
- Nebius · published 2025-10-20 · reviewed 2026-10-08
Operator announces AI Cloud deployment at a Modiin colocation facility using NVIDIA Blackwell infrastructure. Its 4,000 HGX B200 wording describes the wider deployment and is not the government’s 1,000-accelerator allocation or audited present hardware utilization. Location and deployment claims attributed to company.
- Globes / Assaf Gilead · published 2026-01-06 · reviewed 2026-10-08
Original business reporting, including Nebius confirmation and attempted Mega Or inquiry, identifies existing 8 MW Modi’in site hosting the national supercomputer. Describes wider expansion separately. Capacity is reported commercial scope, not measured IT load; future additional 16 MW is not current delivered load.
- Calcalist CTech / Meir Orbach · published 2025-05-14 · reviewed 2026-10-08
Original interview with authority CEO supports competitive award, Blackwell plan and projected funding. Historical early2026 operating forecast is superseded by January 2026 authority confirmation. Interview is independent journalism, but award figures originate with authority, not an independent spending audit.
- Calcalist CTech · published 2026-01-06 · reviewed 2026-10-08
Business reporting describes Mega DC’s earlier 8 MW Modi’in agreement and reported September operation. Expected NIS35 million annual facility NOI is a company forecast; separate Masmiyya/Beit Shemesh 80 MW deal, $880 million construction estimate and NIS300 million NOI do not belong to this campus.
- Nebius · published date not established · reviewed 2026-10-11
March 31 announcement: up to 310 MW planned full campus; first customer capacity targeted for 2027.
- City of Lappeenranta · published date not established · reviewed 2026-10-11
Municipal record: Pajarila location, city land lease, Polarnode development role and Nebius operator role.
- Yle · published date not established · reviewed 2026-10-11
August 11 reporting: building work began July 2026; Fira first-phase main contractor.
- Yle · published date not established · reviewed 2026-10-11
September follow-up: site clearing began March 2026.
- City of Lappeenranta · published date not established · reviewed 2026-10-11
Municipal FAQ: site and infrastructure context; participant-attributed answers are labeled.
- Caverion · published date not established · reviewed 2026-10-12
May 13, 2026 contractor disclosure: approximately EUR 15 million substation agreement; 70 MW first phase and spring 2027 completion target. These are electrical infrastructure specifications and expectations, not verified energized IT capacity or customer service.
- TSMC · published date not established · reviewed 2026-10-12
Arizona campus disclosure: first fab N4 high-volume production began Q4 2024; second fab N3 production targeted second-half 2027; third fab N2/A16 planned by decade end; fourth fab and first packaging plant initial construction begun in early 2026. USD 265 billion is an announced investment envelope.
- Arizona Commerce Authority · published date not established · reviewed 2026-10-12
July 16 announcement describes another USD 100 billion, bringing the announced Arizona plan to USD 265 billion and 10 fabs, two packaging facilities and R&D. This is announced scope, not delivered facilities, paid spending or a blanket construction permit.
- City of Phoenix · published date not established · reviewed 2026-10-12
Documents Fab 3 topping-out ceremony May 5. A highest-beam building milestone is not tool installation, production qualification or operating acceptance.
- Reuters · published date not established · reviewed 2026-10-12
Reports additional Arizona investment and management’s market-dependent expansion timing; corroborates the announcement, not completion.
- NVIDIA · published date not established · reviewed 2026-10-12
Reports Blackwell wafer volume production at TSMC Phoenix. Wafer production is not evidence of all-US packaging or Arizona revenue allocation.
- NIST / U.S. Commerce · published date not established · reviewed 2026-10-12
Up to USD 6.6 billion direct funding for the historical more-than-USD-65-billion three-fab scope; milestone-based disbursement. Up to USD 5 billion proposed loans; not proof of full disbursement or funding for all later expansion.
- Phoenix City Council · published date not established · reviewed 2026-10-12
File 26-0966, Ordinance S-52899: adopted wastewater-development authorization, infrastructure costs assigned to TSMC, reclamation conditions and June 30, 2028 initial-plant deadline in the summary. Adoption does not prove execution of agreement or completed works.
- Maricopa County Air Quality · published date not established · reviewed 2026-10-12
Lists TSMC Phoenix Project, facility F041443, 5088 Innovation Circle, as Active. Index is not a complete permit-condition, amendment or compliance audit.
- Amkor / TSMC · published date not established · reviewed 2026-10-12
10-year Arizona packaging/testing procurement collaboration; partner campus distinct from TSMC fabs and its own packaging facility. Contract allocation and realized revenue not disclosed.
- GlobalFoundries · published date not established · reviewed 2026-10-12
USD 2 billion initial five-year TSMC interposer manufacturing agreement, Malta New York, volume ramp targeted first-half 2028. Supply-chain context, not a Phoenix fab or verified Arizona allocation.
- Apple · published date not established · reviewed 2026-10-12
Reports being on track to purchase well over 100 million TSMC Arizona chips in 2026. This is a sourcing expectation, not audited final annual purchases or an AI-only workload allocation.
- TSMC · published date not established · reviewed 2026-10-12
Original USD 12 billion plan and 20,000-wafer/month target, not current measured output.
- TSMC · published date not established · reviewed 2026-10-12
Two-fab USD 40 billion historical scope. Earlier targets are not substituted for current production evidence.
- TSMC / SEC · published date not established · reviewed 2026-10-12
USD 165 billion expansion envelope with further fabs, packaging and R&D; issuer-authored filing, not independent corroboration.
- TSMC · published date not established · reviewed 2026-10-12
Facilities, equipment and process technician training with education partners. Programme existence does not establish workforce sufficiency or production ramp success.
- EPA · published date not established · reviewed 2026-10-12
Core/shell versus emissions-unit construction correspondence. Applicant positions are separated from EPA response; not a campus-wide operating permit.
- Reuters · published date not established · reviewed 2026-10-12
Reports executive goal for Arizona CoWoS/3D-IC capability before 2029. Target, not delivered capability.
- NIST / U.S. Commerce · published date not established · reviewed 2026-10-12
Reports USD 265 billion planned investment and total 12 manufacturing/packaging facilities; not 12 operating wafer fabs.
- TSMC · published date not established · reviewed 2026-10-12
October 15, 2026 earnings conference is the next company disclosure checkpoint; future results are not known.
- Amkor / TSMC · published date not established · reviewed 2026-10-12
Original memorandum describes planned Peoria packaging/test collaboration for TSMC Phoenix customers; no completed partner capability established.
- TSMC · published date not established · reviewed 2026-10-12
2025 annual filing confirms first Arizona fab high-volume production at end-2024, additional land acquired in 2026, and conditions, compliance and project milestones attached to CHIPS funding.
- TSMC investor relations · published date not established · reviewed 2026-10-12
Management discusses Arizona expansion, global USD 60–64 billion 2026 capital budget and collective overseas-fab gross-margin dilution. Guidance is not site-level expenditure or Arizona-only profitability.
- TSMC / SEC · published date not established · reviewed 2026-10-12
Board approved second-quarter financial statements and approximately USD 29.4425 billion capital appropriations for advanced technology, packaging and fab facilities. Appropriations are companywide authorizations, not Arizona expenditure or an amount to add to annual capital guidance.