Microsoft Bergheim/Paffendorf: permits, power scope and investor evidence
FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →
Project status: March 2026 groundbreaking and building permits reported; phase-one backup application documented; commissioning unverified. Capacity scope: IT MW not established; 297.4 MW is phase-one backup thermal input, excluded from computing and grid-capacity totals. How we verify evidence.
Published and source checked October 14, 2026. Construction initiation; customer operation unverified.
English · Deutsch · FJ Intelligence
Project scope
Track Bergheim/Paffendorf as one campus, not the entire Rhenish cluster. The state record names NRW01, NRW02 and NRW03; the first phase covers NRW01 and shared infrastructure. Bedburg, Elsdorf and Grevenbroich are separate locations.
Construction and regulatory boundary
Microsoft reported the March 12, 2026 ceremony and issued building permits. The later Cologne procedure concerns phase-one backup equipment. An ended consultation does not establish a final authorization; a groundbreaking does not prove commissioning.
Power: thermal input is not computing capacity
The 297.4 MW figure measures combustion thermal input for backup generation. IT MW, binding grid capacity and current energized computing are not established. FJI stores the thermal measurement separately and excludes it from operating-load totals.
Capital and company exposure
RWE’s annual report identifies the April 2024 land sale. Microsoft’s EUR 3.2 billion announcement has Germany-wide scope. Neither establishes Bergheim expenditure, financing close or site earnings. Microsoft is the sponsor; RWE’s verified role is historical land seller.
FJI research question
What was committed to deliver, by when, and what had actually been delivered or paid at each checkpoint? Land sale, construction initiation, permit application and customer acceptance are different stages. No like-for-like delivery variance can yet be calculated.
Investor interpretation · Our analysis
This case adds evidence about the transition from industrial land to cloud infrastructure. A company may monetize land before the cloud operator earns service revenue. A separate backup-permit dependency can remain after building approval. These are research hypotheses to test across projects, not evidence of an industry-wide delay or power shortfall.
Next evidence and invalidation tests
A published final decision would resolve the application milestone. Dated grid and commissioning records could establish usable capacity. Campus-specific financial disclosures could support economic attribution. Until then, operating IT MW, delivered capacity and paid project capex remain unknown. No unnamed chip, equipment or utility supplier is assigned exposure.
Sources and claim boundaries
- Bezirksregierung Köln / Beteiligung NRW
Cologne regulator identifies Microsoft Deutschland MCIO GmbH as applicant at Bergheim/Paffendorf, K41, parcel 269, Flur 009. Phase 1 is NRW01 and infrastructure for NRW02/03. The backup-generator application specifies 297.4 MW thermal input; this is neither IT load nor grid capacity. Participation ran May 26–July 27, 2026; closure is not an approval decision.
Document date: not established · checked October 14, 2026
- Microsoft
Microsoft reports a March 12, 2026 symbolic groundbreaking in Bergheim and issued building permits for Bergheim and Bedburg. This confirms an initiation milestone, not commissioning or current completion. Bergheim is distinct from the other regional campuses.
Document date: 2026-03-12 · checked October 14, 2026
- RWE Annual Report 2024
RWE Annual Report 2024, printed page 39 (PDF page 39), records an April 2024 Bergheim land sale to Microsoft. It establishes a historical land-vendor role, not a campus electricity contract or recurring operating exposure. No transaction price is allocated here.
Document date: 2025-03-20 · checked October 14, 2026
- Microsoft
Microsoft described a EUR 3.2 billion Germany investment package on March 18, 2024, with the Rhenish region a focus. The envelope is not Bergheim-only capex, closed project financing or actual spending.
Document date: 2024-03-18 · checked October 14, 2026
- Germany Trade & Invest
Germany Trade & Invest describes the Bergheim ceremony within a wider program spanning Bergheim, Bedburg, Elsdorf and an additional Hesse site. Its April 2, 2026 account corroborates the multi-site scope, not a Bergheim investment allocation.
Document date: 2026-04-02 · checked October 14, 2026
Microsoft company research → · RWE: scoped project exposure → · Compare · Track milestones
Company investor information & quarterly statements
Microsoft
Cloud infrastructure sponsor; German subsidiary named regulatory applicant.
Official investor & shareholder information · Quarterly financial statements: FY2026 Q4, quarter ended June 30, 2026
RWE
Historical Bergheim land seller, April 2024; no campus power-supply role established.
Official investor & shareholder information · Quarterly financial statements: H1 2026 includes April–June2026 quarter
Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →