Europe · Finland

Microsoft Vihti / Huhmari campus

FJI source-qualified: four-document gate met, including project-specific government evidence. Qualification evidence and decisions →

Published and scoped evidence reviewed October 16, 2026. Historical source events retain their own dates.

Microsoft research · FJI evidence · Compare · Milestones · European coverage

Project at a glance

Location
Rosti business park / Huhmari, Vihti, Finland
Status
Municipal permit and Microsoft contractor updates document a distinct campus under development and construction
Capacity scope
Campus operating IT MW unavailable; land and regional energy figures excluded from IT totals.
Business model
Phased hyperscale cloud and AI-supporting infrastructure
Next milestone
Check permit 927-406-5-201 disposition, phase completion and customer-service commencement.

Representative locality-area pin, not a surveyed campus boundary or entrance.

Three campuses, one region

Vihti is physically separate from Espoo and Kirkkonummi. The municipality explicitly describes the independently functioning locations, supporting three project records without an extra parent-region record.

Land and permit evidence

Vihti reports two plots of about 46 hectares, a EUR12.3 million land deal and a later building-permit notice for Hankasalontie 12. None establishes total campus expenditure.

Investor read-through

Our analysis: permit progression and contractor mobilisation support a delivery-monitoring case, while commissioning remains a separate future checkpoint.

Delivery commitments and dated checkpoints

Target: Regional first-phase construction target around year-end 2026–2027; commissioning follows.

Unavailable: no matched, comparable accepted operating-IT target and actual.

Company connections

Microsoft develops Vihti; Microsoft 3465 Finland Oy is the named permit applicant. Mercury is an issuer-identified contractor, with no contract economics established.

Microsoft research · FJI evidence · Compare · Milestones · European coverage

What remains unverified

Energization, commissioning, accepted customer capacity, current operating IT MW, utilisation, project spending and campus earnings remain unverified. Current reconsideration/appeal disposition and final building compliance remain open.

Next observable evidence

Check permit 927-406-5-201 disposition, phase completion and customer-service commencement.

Sources and claim boundaries

Documents are counted as documents, not independent confirmations. Same-issuer releases and their rewrites share an underlying claim. Five documents; two municipal records provide separate land/permit evidence. Microsoft updates are issuer claims; DCD gives outside reporting but not independent metering or a complete permit audit.

  1. Municipality of Vihti · 2026-03-13

    Vihti reports a building permit for Microsoft 3465 Finland Oy at Hankasalontie 12, parcel 927-406-5-201, with start rights against security and a reconsideration deadline.

    Original municipal building-permit decision notice · Decision notice paragraphs; March 27, 2026 reconsideration deadline; no current appeal disposition established · Checked 2026-10-16

  2. Municipality of Vihti · 2023-06-27

    Vihti reports a June 15 deed for two plots totalling about 46 hectares and EUR12.3 million. It explicitly describes three separate, independently functioning Finnish sites.

    Original municipal land transaction · Opening land-transaction paragraphs and three-site description · Checked 2026-10-16

  3. Microsoft · Document date not displayed; dated subsection retained

    Microsoft identifies Mercury as main contractor from June 2025 and continuing site work at Vihti; its latest labelled construction update is November 2025.

    Original company construction update · Main contractor change; Construction update November 2025 · Checked 2026-10-16

  4. Microsoft · 2026-04-28

    Microsoft identifies three separate campuses and phased delivery; first-phase building work targets the turn of 2026–2027, followed by commissioning preparation. Second-phase permits are issuer-reported.

    Original company disclosure · Paragraphs 1–5; construction completion and commissioning are separate · Checked 2026-10-16

  5. DatacenterDynamics / Georgia Butler · 2026-06-09

    DCD separately identifies Espoo, Kirkkonummi and Vihti as developments, while attributing site-progress details to Microsoft. Its Vaasa land acquisition is another project.

    Independent specialist reporting; construction details attributed to Microsoft · Finland cloud-region background and links to all three local project updates · Checked 2026-10-16

Structured source audit

AI-assisted public-source research by Fjord Journal. No original interviews, site visits, independent metering or whole-project certification. Planned investment and capacity are excluded from delivered-IT and paid-spending aggregates. Unknown values remain unavailable.

Company investor information & quarterly statements

Microsoft

Microsoft develops Vihti; Microsoft 3465 Finland Oy is the named permit applicant. Mercury is an issuer-identified contractor, with no contract economics established.

Official investor & shareholder information · Quarterly financial statements: FY2026 Q4, quarter ended June 30, 2026

Corporate disclosures provide company-wide context. They do not establish this project’s revenue, spending, profit, ownership share or operating capacity. Disclosure verification records →

Company research: documented roles

Follow the company profile for financial context. The evidence supports the specific role described here.

Role evidence does not establish project revenue, ownership economics, accepted capacity or a percentage of company sales.